> Home

> About Us...

> Design & Install

> Service & Support

> Contact Us

Click here for details
Click here order our latest brochure

 

  < PowaPlus Home

Project Case Studies

POWERTECNIQUE – PROVEN EXPERTISE

Powertecnique was formed in 1991 as a specialist one stop solution provider of tailored, standby power supply equipment. Our project engineering expertise encompasses the design, build and installation of multi-module UPS and generator systems. We offer our clients power supply solutions based upon field proven products and expertise, supported by nationwide aftersales service support. Powertecnique International was first registered in 1998 and continues the same philosophy of close customer support to its international client base.

2 x 3MVA 11kV MOBILE GENERATOR SETS
ABU AL KASIB, IRAQ

Powertecnique were given the challenging task of designing, manufacturing and installing two mobile 2.8MVA 11kV generator sets for the Abu Al Kasib power distribution centre near Basrah. Powertecnique’s brief was to provide generators that could be installed and operate on a six months continuous basis within a high temperature environment, supplying temporary power to the Abu Al Kasib region. After six months the sets had to be capable of being removed and relocated to another site. Fuel tanks, large enough for three days continuous operation, were also to be incorporated, again capable of being relocated.

The design consists of utilising two 2.8MVA high voltage generator sets specially configured for severe ambient temperature together with two 40,000 litre bulk storage tanks and associated transfer system with 11kV switchgear. All items were designed to be mobile with skeletal and flatbed tri-axle trailers.

The generator sets incorporate fully automatic synchroninsing equipment for black start and island operation as well as being capable of paralleling the local grid for G5/9 (G7/5) peak lopping duties. As the regions demand exceeds the rating of the generator sets during peak operating periods, the switchgear allows for preference tripping which will automatically disconnect and reconnect loads to ensure the local region, which is mainly residential, receives power during the day albeit for a timed period.

Specific attention was given to designing the system so it can be transported by air for rapid deployment and to any location. This also extended to a rapid manufacturing program due to the urgency to complete installation before the start of the hot season.

Powertecnique personnel will supervise local Iraqi labour to complete the installation of the site as well as undertaking the testing and commissioning of the complete system prior to handover. An ongoing maintenance and service contract ensures the sets will continue to run in peak condition.

2 X 1MVA GENERATOR SETS
SOUTHMEAD HOSPITAL, BRISTOL, UK

Powertecnique has recently designed, built and installed 2 x 1MVA diesel generator sets complete with auto-synchronising change-over panel, 27,000 litre and 64,000 litre bulk storage tanks and fuel transfer system.

The project was managed by Powertecnique and we undertook all electrical, mechanical and civil work as well as full on-site testing and commissioning of the system. All works had to be carried out with the minimum disruption to the day-to-day running of the hospital.

The generator was designed and custom-built in accordance with the latest NHS Health Technical Memorandum’s. The acoustic canopy was also built to specification and has removable side panels and an all round internal walkway to provide easy access for essential ongoing maintenance.

1 x 500kVA GENERATOR SET
DOVER IMMIGRATION RETURNS CENTRE, UK

 

The client required a generator solution that would power their entire site for at least 200hrs. Before the new generator could be installed the client requested that the existing generator was decommissioned and removed from site and a temporary set provided whist the new set is installed. Disruption to the site’s power supply had to be kept to an absolute minimum.

The solution supplied consisted of a 500kVA POWAPLUS generator set with a 17,000 litre environmental bunded fuel tank and transfer system. The generator is a bespoke design that will provide enough power to the site for several days.

The weatherproof acoustic enclosure was designed to achieve a noise level 65dBA @ 1 metre with lockable door furniture for security and painted in high specification 4 coat finish suitable for offshore/coastal environments.

To keep the generator noise levels to a minimum the gen-set was mounted on a fabricated, steel welded channel base frame to prevent undue vibration transmission.

Powertecnique undertook construction of the base, trenches, cable ducts, cable installation and all electrical and mechanical services to provide a fully functional installation.

Should you require further information on our recent projects or would like to visit a reference site please contact our sales office for further details.